Changes to key current regulations are being prepared
Amendments to the key current regulatory acts of the industrial infrastructure sector are being prepared – RF PP No. 794 and RF PP No. 1119
➡Amendments planned to be made to RF PP No. 794:
- introduction of the concept of “investment partner”; this change will help attract third-party investors to the implementation of the project for the construction and operation of the project infrastructure.
- clarification of requirements for the territory and infrastructure: the maximum permissible distance between land plots that make up the park territory has been increased from 2 to 10 kilometers;
- alternative methods of confirming rights to objects and simplified requirements for the execution of copies of contracts, as well as the ability to confirm the presence of infrastructure through commission acts of inspection of the territory and adjacent territory;
➡Amendments planned to be made to RF PP No. 1119:
- reduction of target indicators for the use of subsidies for regions – for revenue, jobs and investment volume;
- the possibility of reimbursement of regional costs through regional development institutions; – an increase in the maximum amount of expenses subject to reimbursement to regions: for industrial parks from 30 to 45 million rubles per 1 hectare; for technology parks – from 120 thousand to 180 thousand rubles per 1 m² of facility area.